Boundary Road to Holdom Avenue and Kensington Avenue to Cliff Avenue: Upgrade signage, pavement markings, speed humps, intersection improvements at five locations.
Kensington Park from Holdom Avenue to Fell Avenue: New 4.0m multi-use pathway on the south side of the street, including new curb and gutter, urban drainage system, and new streetlights on the south side of the street.
Fell Avenue to Hastings Street to Hammarskjold Drive to Kensington Avenue: Multi-use pathway upgrades including pathway widening and lighting along select segments.
Union Street from Kensington Avenue to Duthie Avenue: Local street bikeway upgrades.
Duthie Avenue from Union Street to Hastings Street: New protected bicycle lanes.
Hastings Street/Burnaby Mountain Parkway from Duthie Avenue to Centennial Way: Remove existing parking and construct a 4.5m multi-use pathway along the south side.
Burnaby Mountain Parkway from Centennial Way to Gaglardi Way: Reallocate existing southbound/eastbound travel lane and painted bike lane into a multi-use path on the south side.